Saturday Gang Volunteer preparing some platework for use |
Introdution:
November was rather quiet compared to previous months. The K&ESR enjoyed a mini winter shutdown which meant all of the locos were in the yard (where we like them!). However to say November isn't a busy month for the Saturday Gang & the Loco Dept would be inaccurate. We have a small window to get our loco fleet ready for an intense period of running in December. The Santa Specials are an integral part of the K&ESR's business plan so without any locos that would cause issues!
November is also a rather grim time of month, it's been cold, raining and the days are short. However this is where all of us show our commitment, rather than pulling the duvet back over the head we get up and head out. We are a self motivated group, we really want to progress and make things happen. Not only that though there really is a social side to the Saturday Gang, the amount of laughter and noise would certainly suggest we're a bit more than colleagues. It's an opportunity for each of us to discuss and listen to others. Our new volunteers who have easily become a part of our group, yes we are a close knit group but that doesn't make us a clique. Really the point here is that its not just our enthusiasm for our work, but also the fun & friendship we have. This is what motivates us to come to Rolvenden rather than do the million other things available.
So if you're at all interested in locomotive overhaul's / maintenance then please get in touch. We are more than happy to show potential volunteers around and / or arrange taster days. You can contact us via email at saturdaygang@gmail.com.
Onwards to the works section.
25 Northiam:
Saturday Gang volunteers preparing the horn guides for the axleboxes |
Further preparatory work has been undertaken to continue the motion reassembly and ultimately re-wheel (see December's report when it arrives!). Work was undertaken on the brake gear and hopefully this will be fitted during December. This includes tasks such as retrieving 25's springs and cleaning out the grease nipples. Although securely stored it doesn't take much to clog up these small parts.
DS238 Wainwright
DS238 under overhaul |
753 P Class
No progress since last report.
In the works / news
23 Holman F Stephens: The boiler washout & mechanical exam unearthed some issues and repairs that needed to be undertaken before Christmas rather than after. We detailed in the previous report many of the issues we had encountered. November saw us finishing off these repairs and re-assembling the loco. We were pleased these were completed at the end of November so 23 will be available for the Santa Specials.
Two Saturday Gang volunteers refitting 23's dome cover |
1638: A 12 month boiler ticket extension has been granted and all the necessary repair work has been carried out. The loco was steam tested and after some fettling returned to traffic. A decision was made to return 1638 to its original BR Black colour it arrived at the K&ESR wearing in 1992.
1638: Back and in black. |
6619: Repairs ongoing.
Class 2 fleet (32670 Bodiam, 32678 Knowle, 14 Charwelton): Winterised and receiving some repairs / maintenance where required.
32678: Winterised. |
Video / Pictures from November
Below is the link to the video for November's report: Apologies but blogger but can't seem to find it to embed so just copy the link and it will take you to the video:
Saturday Gang Video Report November 2013
Saturday Gang Video Report November 2013
We have updated our photo website also so please visit: www.kesrloco.co.uk
If you haven't already please "like" us on Facebook: Saturday Gang Facebook Page
Many thanks for reading, December's report & a review of 2013 will appear in due course.
Saturday Gang
No comments:
Post a Comment