Introduction
Volunteers working on 25's boiler, note the access staging |
Locos are coming out of traffic in quick succession, n.os 23 & 1638 have both been withdrawn from service upon expiry of their boiler tickets. This has reduced the pool of 'Class 5' locos quite substantially (the K&ESR rates locos according to how many MK1 carriages they can pull). With 6619 due out at the end of the year this will present challenges in 2015. However we're always up for a challenge!
So without further hesitation, deviation or repetition let's see what's been happening.
Overhauls:
25 Northiam:
Volunteer setting up a spring bush for machining |
Removing rivet heads, with a powered chisel |
DS238 Wainwright
DS238 brought 'back down to earth' |
Progress continues to be made on DS238's overhaul: the frames have been lowered back onto the wheels and motion reassembly is progressing. The firebox is coming along too, the cut out section of the outer firebox has been welded up and further works on the outer firebox are underway. Still a long way off returning to service but certainly encouraging signs.
1638 Pannier
1638's boiler, lifted from the frames by the steam crane |
As mentioned in the introduction, 1638's boiler ticket has expired. The loco dept has wasted no time in lifting the boiler out of the frames and dismantling the motion. A full assessment of the works required to return 1638 to service will be done, then begins the process of repairs and reassembly. Although 1638 is in ok mechanical condition it will be few years until she steams again, though once DS238 is completed more attention can be given to 1638.
In the works / news from Rolvenden
32670 Bodiam: Available for service.
32678 Knowle: Available for service.
753 P Class: No progress to report.
12 Marcia: Stored in Orpins sidings awaiting remedial works to begin.
14 Charwelton: Available for service.
P Class awaiting attention |
376 Norwegian: Available for service.
23 Holman F Stephens: Suffered a failure in service which lead to an early withdrawal for overhaul (only a week!). The current plan is to store n.o 23 until other overhauls are completed. During November the Saturday Gang will be stripping n.o 23 and preparing for her for storage. All the components such as ejectors, gauges, piping etc will be placed into secure storage.
23 Holman F Stephens: Suffered a failure in service which lead to an early withdrawal for overhaul (only a week!). The current plan is to store n.o 23 until other overhauls are completed. During November the Saturday Gang will be stripping n.o 23 and preparing for her for storage. All the components such as ejectors, gauges, piping etc will be placed into secure storage.
6619: Repairs / washout completed. Available for service.
65 Maunsell: Available for service.
6619 shortly before works completed |
Videos
Two video reports are available, covering both September & October.
September 2014:
October 2014:
Many thanks for reading,
Saturday Gang
No comments:
Post a Comment